December 23, 2002
Subject: Opportunity to Participate in Test Equipment (ILRT/SIT), Package
No. 9-185-J208
The Korean Peninsula Energy Development Organization (KEDO) is offering
companies from KEDO Member Countries an opportunity to participate in
the procurement of materials, components, and equipment for the construction
of its Light Water Reactor Project in Kumho, North Korea.
This particular opportunity is for the supply of test equipment (ILRT/SIT).
Interested companies who possess the technical capability, production
capacity, and financial stability to offer a competitively priced product
are encouraged to respond. KEDO will review the responses from interested
companies and compile a consolidated list of candidates. This list will
be forwarded to Korea Electric Power Corporation (KEPCO), the Prime Contractor,
with instructions to qualify these companies for inclusion in their Pool
of Qualified Suppliers.
Any company interested, and who deems themselves capable of being qualified
in providing test equipment (ILRT/SIT) is encouraged to complete the enclosed
brief corporate overview and return it with any additional relevant corporate
information to KEDO before the close of business on February 3, 2003.
A brief summary of the technical specification for this procurement is
enclosed to assist companies in making a determination to participate.
This information is also posted on KEDO's Web Page at www.kedo.org.
Companies selected by KEDO to be considered for this procurement should
receive a qualification package from KEPCO around mid April 2003.
If you have any questions regarding this opportunity, please feel free
to contact Mr. Soon nam Jung at (212) 455-0207.
Sincerely,
John B. Mulligan
Director, Project Operations Division
SPEC NO:
|
9-185-J208 |
TITLE:
|
Test Equipment (ILRT/SIT)
|
PROCUREMENT SOURCE:
|
OB
|
QUALITY CLASS:
|
S
|
FORECASTED ITT ISSUE DATE:
|
October 15, 2003 |
FORECASTED CONTRACT AWARD DATE:
|
August 15, 2004 |
FORCASTED INITIAL SITE DELIVERY DATE:
|
December 31, 2005 |
DESCRIPTION:
|
a. Safety Category: Non-Safety Related
|
b. Relevant
Codes and Standards (in effect as of December 31, 1996):
- USNRC-SRP 6.2.6
- USNRC 10 CFR 50
- ANSI N45.4, ANSI/ANS 56.8
- ASME NQA-1¹
|
c. Scope of
Supply (for two 1000 MWe units)
- SIT Equipment (1 set)
- ILRT Equipment (1set)
|
d. Design Requirements
- Test equipment furnished under this specification shall be
designed to meet the requirements of the codes and standards and
this specification including the supplemental information in Attachments
and Appendices, as applicable.
- All test equipment requiring AC power shall be suitable for
120VAC+/- 10%, 60Hz +/- 5%, single phase.
- The cables that are furnished under this specification shall
meet the vertical flame test requirements of IEEE-383.
|
e. Technical
Requirements
- Shop Calibration: The supplier shall calibrate all applicable
instruments in accordance with his standard specification.
- Certification: The supplier shall submit a certificate of compliance
stating that applicable instruments have been calibrated.
- Inspection of the equipment may be at the supplier's factory
or upon receipt at destination, at the option of KEPCO's duly
authorized representative.
|
¹ Note: The extent to which the QA requirements are to be applied shall be consistent with the importance to nuclear safety of the item, service or process. A graded approach, which can satisfy the necessary requirements and ensure the required quality and safety,shall be used.
|
|